LogoLogo
FRC Build System
  • Overview and Features
  • General Info
    • Individual Components
  • Assembly Instructions
    • Getting Started
    • OMIO CNC Router Stand (Mobile Cart)
      • Steps 1-4
      • Steps 5-8
      • Steps 9-13
      • Leveling The Router Stand
    • Installing OMIO X8 CNC Router
    • OMIO CNC Router Enclosure (Base)
      • Steps 1-4
      • Steps 5-8
      • Steps 9-12
    • Installing Router Enclosure
  • Misc
    • FAQ & Trouble Shooting
    • Changelog
Powered by GitBook
On this page
  • Step 5
  • Step 6
  • Step 7
  • Step 8
Export as PDF
  1. Assembly Instructions
  2. OMIO CNC Router Stand (Mobile Cart)

Steps 5-8

PreviousSteps 1-4NextSteps 9-13

Last updated 3 days ago

Vibra-TITE VC-3 Threadmate () is recommended on all bolts that thread into a tapped hole.

Step 5

Install all tubes as shown in the locations shown below. Use four #10-32 x 3/8”L bolts to secure each end of tube in place. Rivnuts need to be facing up on each tube.

Step 6

Install all tubes as shown in the locations shown below. Use four #10-32 x 3/8”L bolts to secure each end of tube in place. Rivnuts need to be facing up on each tube.

Step 7

Place the MDF Short Shelf and MDF Long Shelf on top of the aluminum structure from the previous step. The counter bores in the MDF Shelf will line up with the rivnuts in the tubing. Install all #10-32 x 1.25”L bolts.

DO NOT over tighten the bolts.

Step 8

Install all tubes as shown in the locations shown below. Use four #10-32 x 3/8”L bolts to secure each end of tube in place. Install as many sets of dividers as desired.

Some angle iron may be installed on the wood base directly under each 1” x 1” piece of tubing to help prevent sheets from sliding around, if the cart will be moved often. This is an optional addition and parts are not included.