The installation of the Snap-in Nuts into the Horizontal Rails will be demonstrated below.
The location of the Snap-in Nuts can vary as it is based on the bin sizes used.
Insert the Snap-in Nuts into the corresponding slots.
Repeat this step for the second Right Case Horizontal Rail
Insert the Snap-in Nuts into the corresponding slots.
Repeat this step for the second Left Case Horizontal Rail
The installation of the Snap-in Nuts into the Vertical Rails will be demonstrated below.
The location of the Snap-in Nuts can vary as it is based on the bin sizes used.
Insert the Snap-in Nuts into the corresponding slots.
Repeat this step for the second Left Case Vertical Rail
Insert the Snap-in Nuts into the corresponding slots.
Repeat this step for the second Right Case Vertical Rail
Insert the Snap-in Nuts into the corresponding slots.
Repeat this step for a second Middle Middle Rail (Tube 1)
Insert the Snap-in Nuts into the corresponding slots.
Repeat this step for a second Middle Middle Rail (Tube 2)
The reference picture above shows the installation of half of the Snap-in Nuts that are needed. The picture below shows the finished product.
Insert the Snap-in Nuts into the corresponding slots.
Repeat this step until you have six of the Middle Rail (Tube 3).
The reference picture above shows the installation of half of the Snap-in Nuts that are needed. The picture below shows the finished product.
Take the Vertical Rail Tubes from Step 2 and install them onto the Horizontal Rail Tubes using #10-32 x .500" L bolts into the snap nuts.
The spacing of the vertical rails is based on the bin sizes used.
Repeat this step for the other half of the Single Upper Kit.
Take the bin rails and install them onto the vertical rails using #10-32 x .500" L bolts into the snap nuts.
Only install the bottom row of bin rails.