# Structure

{% hint style="success" %}
The following images show #10-32 Rivnuts installed in the Structure Tubes. The use of Rivnuts is meant to make the repeated removal and install of the  Fixed Side Panels hassle-free. However this is completely optional and does not need to be done.&#x20;
{% endhint %}

## Step 1

Install a 2" x 1" Tube Plug into each end of the of the Vertical Structure Tubes using two #10-32 x 3/8"L bolts as shown below. Additional bolts will be added in later assembly steps.

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FC5RwmstqutCi4vOhkOqH%2FCC2026%20Structure%20Manual%20-%20Step%201.svg?alt=media&#x26;token=aecaa055-2a54-4d4b-894c-00c217794167" alt=""><figcaption></figcaption></figure>

## Step 2

Install a 1" x 1" Tube Plug into each end of the Horizontal Rails using #10-32 x 3/8"L bolt as shown below. Additional bolts will be added in later assembly steps.

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2F3BkmvHpRqbc4YqUXd5OA%2FCC2026%20Structure%20Manual%20-%20Step%202.svg?alt=media&#x26;token=aaf5e506-d573-4bf2-8c40-b156f8995a52" alt=""><figcaption></figcaption></figure>

## Step 3

Install and fully capture a 1/2" Rounded He  using a Bearing Retention Plate and Roller Center Plates as shown below. Secure the plates using #10-32 bolts.

{% hint style="info" %}
Repeat this for the second Vertical Rail.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FdZoNd1ukEeT7Xu2KUAao%2FCC2026%20Structure%20Manual%20-%20Step%203.svg?alt=media&#x26;token=95a93c38-c9b6-49f5-8d1d-2dfa2478e58d" alt=""><figcaption></figcaption></figure>

## Step 4

Mount the Horizontal Rails from Step 2 onto the Vertical Rail from Step 3 using #10-32 bolts as shown  below.

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2F7wYUJbeN385UDhSxB2Kn%2FCC2026%20Structure%20Manual%20-%20Step%204.svg?alt=media&#x26;token=3fee2782-3375-4280-bd55-b91f0eb608bf" alt=""><figcaption></figcaption></figure>

## Step 5

Install T Gussets onto the assembly from Step 4 using #10-32 x 3/8"L Bolts and 3/16" Rivets.&#x20;

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FA0Or4YnAAER0RCeu0QE4%2FCC2026%20Structure%20Manual%20-%20Step%205.svg?alt=media&#x26;token=c664399b-a7a5-4008-9ee3-7b7fe54618ef" alt=""><figcaption></figcaption></figure>

## Step 6

Install the 1.5" x 1.5" Support Tube to the assembly from Step 5 using the Gussets and hardware shown below.

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FRXGEg3so35WxD8xIWTaX%2FCC2026%20Structure%20Manual%20-%20Step%206.svg?alt=media&#x26;token=cb65ac7e-dde3-4d94-8a3f-0ae341021173" alt=""><figcaption></figcaption></figure>

## Step 7

Install the Plastic Hopper Guard onto the Assembly from Step 6 using #10-32 x 1-1/2"L Bolt and Nuts.

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FLPdvEaaMxFjrFuPOerem%2FCC2026%20Structure%20Manual%20-%20Step%207.svg?alt=media&#x26;token=5ebfcbe5-271a-48a4-881b-aacbe9afe671" alt=""><figcaption></figcaption></figure>

## Step 8

Install two 90 Degree Mounting Brackets to the Vertical Structure Tubes from Step 7 using #10-32 x 3/8"L Bolts.

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FQyxm8OMaHgX1efCph98n%2FCC2026%20Structure%20Manual%20-%20Step%208.svg?alt=media&#x26;token=5fa64147-3c99-4793-983a-8b25b4ff32b2" alt=""><figcaption></figcaption></figure>

## Step 9

{% hint style="info" %}
The image below show the Assembled Stage #1 Bottom Block already installed. For detailed information on this refer back to the <a href="https://app.gitbook.com/o/jQ1oA79yIGzA6fO0uMWk/s/v4uWgoa2pyoF3A7EV9YD/" class="button primary" data-icon="book-open">Telescope Manual</a>
{% endhint %}

Install the Hooks onto the 1" x 1" Hook Tube using the appropriate #10-32 Bolts and Nuts as shown below.&#x20;

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FGpJ0b5UPVRIoxd2ZnilX%2FCC2026%20Structure%20Manual%20-%20Step%209.svg?alt=media&#x26;token=e1d5725f-b3e3-4e04-b587-7e060c93be2d" alt=""><figcaption></figcaption></figure>

## Step 10

Install the Hook assembly from Step 9 to the Structure assembly from Step 8.

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FuBSFd0Fv4zBCaYGDJ4Qc%2FCC2026%20Structure%20Manual%20-%20Step%2010.svg?alt=media&#x26;token=edfe7d51-9ad8-4f74-830f-ef123e6eec33" alt=""><figcaption></figcaption></figure>

## Step 11

{% hint style="info" %}
Repeat this for the other half of the Structure assembly.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2FfutaQfW4WURd1uMmmlcZ%2FCC2026%20Structure%20Manual%20-%20Step%2011.svg?alt=media&#x26;token=f7315e53-14b1-49b0-b8fb-c8b5900a09d6" alt=""><figcaption></figcaption></figure>

## Step 12

Press a 5/8" ID Tube Connecting Nut into each end of the 3/4" OD Standoffs.&#x20;

Installing the Tube Connecting Nuts can be done using an Arbor press or a dead blow hammer.

{% hint style="info" %}
The 3/4" OD tubes are referred to as **Standoffs**, as they are used to add rigidity to the assembled Hopper.
{% endhint %}

<figure><img src="https://1013940090-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6vNqagDHjOasMNxIK8L6%2Fuploads%2F4D9ZWwhIFrdQZAbhwZXc%2FCC2026%20Structure%20Manual%20-%20Step%2012.svg?alt=media&#x26;token=f70893ab-fbe5-4019-8f20-c3769b7652a6" alt=""><figcaption></figcaption></figure>